Sewer work in RP to tie up roads
Construction work starts in November
Bookmark and Share
By Dave Williams  October 18, 2013 12:00 am

The Eastside Trunk Sewer Replacement Project will begin in earnest in November, which will have a significant impact on Rohnert Park drivers.

Avram Drive, Santa Alicia Drive, Seed Farm Drive, Southwest Boulevard and Snyder Lane all will be affected as there are expected to be roadway lane changes or reductions and potential noise impacts during construction, according to the Rohnert Park Dept. of Public Safety. Construction is expected to end in late 2014.

Work will begin at the intersection of Commerce Boulevard and Avram and continue east on Avram. 

Then, construction will continue on to Santa Alicia to Seed Farm Drive. The pipeline will continue south on Seed Farm, divert under the Sonoma-Marin Area Rail Transit (SMART) railroad tracks, continue east on Southwest to Snyder. 

The pipeline goes south on Snyder and ties into the existing sewer system in the intersection of East Cotati Avenue and Snyder. 

Construction activities will include utility construction and pavement restoration. There will be traffic and pedestrian control measures in place during construction.

No work will begin before 8 a.m., and work will end each day at 5 p.m.